Project Description
The Tom Adams Bridge over Lemon Bay ICWW, originally constructed in 1965, is scheduled for repairs to extend its lifespan and ensure continued safe use. This project involves hiring an engineering firm to design the bridge's structural repairs.Project Location
The Tom Adams Bridge is located on Beach Road over the Lemon Bay Intracoastal Waterway.Latest Updates
Project Update - December 2025
The County has completed its review and approved the 60% construction plans. We anticipate receiving the finalized 100% construction plans, specifications, and permits by February 11, 2026.
Budget
| Phase | Cost |
|---|---|
| Design | $182,143.50 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 05/27/2025 | 03/20/2026 |
Project Phase
Design Development
Last Updated
12/16/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
DRMP Engineering