Project Description
This project includes the design and construction of six (6) new turn lanes at various intersections along Veterans Boulevard. The improvements consist of new left and right turn lanes on Veterans Boulevard, along with associated sidewalk modifications, drainage improvements, and street light adjustments.
Project Location
- Veterans Boulevard @ Yorkshire Street
- Veterans Boulevard @ Harbor Boulevard
- Veterans Boulevard @ Orlando Boulevard
- Veterans Boulevard @ Torrington Street
- Veterans Boulevard @ Loveland Boulevard
- Veterans Boulevard @ Norman Street
Project Impacts
Starting on May 18th, the median will be closed to cross traffic while the contractor constructs the new median alignment.Latest Updates
Veterans Boulevard & Yorkshire Street
Construction activities are underway at the intersection of Veterans Boulevard and Yorkshire Street. Crews are currently excavating the median area in preparation for the installation of new concrete curb and gutter, as well as the revised traffic lane configuration.
Veterans Boulevard & Norman Street
Construction activities are progressing at the intersection of Veterans Boulevard and Norman Street. Crews are removing the existing guardrail to facilitate construction of the new right-turn lane and associated roadway improvements.
Budget
| Phase | Cost |
|---|---|
| Design | $970,373.50 |
| Construction | $3,375,027.61 |
| Total Budget | $4,345,401.11 |
Gas Tax C411620
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 02/11/2019 | 08/14/2019 | 08/14/2019 |
| Design Development | 09/02/2020 | 02/20/2026 | 10/16/2025 |
| Construction | 05/18/2026 | 11/14/2026 |
Supporting Materials
Project Phase
Construction
Last Updated
06/01/2026
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
26-286
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
EHC Construction