Project Description
This project incorporates the design and construction of new turn lanes at various intersections along Veterans Boulevard. New left and right turn lanes will be added with sidewalk modifications.
Project Location
- Veterans Boulevard @ Yorkshire Street – right turn lane from east bound Veterans Blvd to south bound Yorkshire Street, right turn lane from west bound Veterans Blvd to north bound Yorkshire Street
- Veterans Boulevard @ Harbor Boulevard – right turn lane from east bound Veterans Blvd to south bound Harbor Blvd
- Veterans Boulevard @ Orlando Boulevard – right turn lane from east bound Veterans Blvd to south bound Orlando Blvd
- Veterans Boulevard @ Torrington Street – right turn lane from east bound Veterans Blvd to south bound Torrington Street
- Veterans Boulevard @ Loveland Boulevard – right turn lane from east bound Veterans Blvd to south bound Loveland Blvd
- Veterans Boulevard @ Norman Street – right turn lane from east bound Veterans Blvd to south bound Norman Street
Latest Updates
Veterans Boulevard @ Loveland Boulevard intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding
Veterans Boulevard @ Torrington Street intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding
Veterans Boulevard @ Harbor Boulevard intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding
Veterans Boulevard @ Yorkshire Street intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding
Veterans Boulevard @ Orlando Boulevard intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding
Veterans Boulevard @ Norman Street intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding
Budget
| Phase | Cost |
|---|---|
| Design | $970,373.50 |
| Construction | $3,722,000.00 |
| Total Budget | $4,692,373.50 |
Gas Tax C411620
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 02/11/2019 | 08/14/2019 | 08/14/2019 |
| Design Development | 09/02/2020 | 02/20/2026 | 10/16/2025 |
| Construction | 03/16/2026 | 09/25/2026 |
Supporting Materials
Project Phase
Design Development
Last Updated
10/27/2025
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
19-279
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
TBD