Veterans Boulevard Intersection Improvements

Project Description

This project incorporates the design and construction of new turn lanes at various intersections along Veterans Boulevard. New left and right turn lanes will be added with sidewalk modifications.

Project Location

  • Veterans Boulevard @ Yorkshire Street – right turn lane from east bound Veterans Blvd to south bound Yorkshire Street, right turn lane from west bound Veterans Blvd to north bound Yorkshire Street
  • Veterans Boulevard @ Harbor Boulevard – right turn lane from east bound Veterans Blvd to south bound Harbor Blvd
  • Veterans Boulevard @ Orlando Boulevard – right turn lane from east bound Veterans Blvd to south bound Orlando Blvd
  • Veterans Boulevard @ Torrington Street – right turn lane from east bound Veterans Blvd to south bound Torrington Street
  • Veterans Boulevard @ Loveland Boulevard – right turn lane from east bound Veterans Blvd to south bound Loveland Blvd
  • Veterans Boulevard @ Norman Street – right turn lane from east bound Veterans Blvd to south bound Norman Street

Latest Updates

Veterans Boulevard @ Loveland Boulevard intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding

Veterans Boulevard @ Torrington Street intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding

Veterans Boulevard @ Harbor Boulevard intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding

Veterans Boulevard @ Yorkshire Street intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding

Veterans Boulevard @ Orlando Boulevard intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding

Veterans Boulevard @ Norman Street intersection. Final plans have been received. Charlotte County is preparing contract documents for bidding

Budget

Phase Cost
Design $970,373.50
Construction $3,722,000.00
Total Budget $4,692,373.50
Funding source(s):

Gas Tax C411620

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 02/11/2019 08/14/2019 08/14/2019
Design Development 09/02/2020 02/20/2026 10/16/2025
Construction 03/16/2026 09/25/2026

Supporting Materials

Veterans Boulevard Intersection Improvements Project Image

Project Phase
Design Development

Last Updated
10/27/2025

Project Manager
Jeff Keyser

Public Relations
Chad Ray
Email Public Relations

Project Number
19-279

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Florida Transportation Engineering

Construction Contractor
TBD