Project Description
The Washington Loop Road Bridges over Shell Creek and Myrtle Slough, originally constructed in 1961, are scheduled for repairs to extend their lifespan and ensure continued safe use. This project includes procuring an engineering firm to design the necessary repairs, followed by contracting with a construction firm to carry out the rehabilitation work.Project Location
Washington Loop Road over Shell Creek Bridge (#010008)
Washington Loop Road over Myrtle Slough Bridge (#010007)
Latest Updates
Project Activity - July 2026
Acros Bridge is currently working on the Bridge Repair Memorandum, which is due on July 24, 2026.
Budget
| Phase | Cost |
|---|---|
| Design | $180,000 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 06/15/2026 | 12/11/2026 |
Project Phase
Design Development
Last Updated
07/09/2026
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Acros Bridges