Project Description
To meet growing infrastructure needs, the Utilities Department is building its first water tower. The concrete pedestal tower will hold two million gallons of water to better support fire flow requirements and peak demands in the south-county service area. The tower will be located near U.S. 41 and Notre Dame Boulevard.
Project Location
Near U.S. 41 and Notre Dame Boulevard.Budget
| Phase | Cost |
|---|---|
| Design | $1,928,800 |
| Construction | $10,946,100 |
| Total Budget | $12,874,900.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/16/2022 | 01/15/2024 | |
| Design Development | 01/15/2024 | 12/31/2025 | 12/17/2025 |
| Construction | 05/01/2026 | 11/15/2026 |
Supporting Materials
Project Phase
Planning and Project Approval
Last Updated
02/05/2026
Public Relations
Stuart Gooden
Email Public Relations
Sponsor Department
Utilities
Design Engineer/Architect
Weston & Sampson