Project Description
To meet evolving infrastructure needs, the Utilities Department is building its first water tower. The concrete pedestal tower will hold two million gallons of water to better support fire flow requirements, provide capacity during peak demand, and improve system resilience during emergencies such as hurricanes. The tank will be located near U.S. 41 and Notre Dame Boulevard.
Project Location
Near U.S. 41 and Notre Dame Boulevard.Budget
| Phase | Cost |
|---|---|
| Design | $1,928,800 |
| Construction | $10,946,100 |
| Total Budget | $12,874,900.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/16/2022 | 01/15/2024 | |
| Design Development | 01/15/2024 | 12/31/2025 | 12/17/2025 |
| Construction | 05/01/2026 | 11/15/2026 |
Supporting Materials
Project Phase
Planning and Project Approval
Last Updated
06/12/2026
Public Relations
Stuart Gooden
Email Public Relations
Sponsor Department
Utilities
Design Engineer/Architect
Weston & Sampson