Project Description
Design & construct a sidewalk on Willmington Boulevard.Project Location
South side of Willmington Boulevard connecting to the existing sidewalk at Pennell Street to Roberta Drive.Latest Updates
The 100% construction plans were received and bid package is assembled. The funding for the construction was not approved at this time it will be put on hold for future funding.Budget
Phase | Cost |
---|---|
Design | $72,970.00 |
Construction | $289,000.00 |
Total Budget | $361,970.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/07/2022 | 03/01/2023 | 03/01/2023 |
Construction | 07/03/2023 | 02/01/2024 |
Project Phase
Planning and Project Approval
Last Updated
08/25/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Giffels-Webster Engineers
Construction Contractor
TBD