Project Description
Design & construct a sidewalk on Willmington Boulevard.Project Location
Willmington Boulevard from Pennell Street to Roberta DriveLatest Updates
The 100% construction plans were received and bid package is being assembled. The MSBU committee has requested to wait until after the FY25 paving bids are opened to look at budgets before going to construction.Budget
Phase | Cost |
---|---|
Design | $72,970.00 |
Construction | $289,000.00 |
Total Budget | $361,970.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/07/2022 | 03/01/2023 | 03/01/2023 |
Construction | 07/03/2023 | 02/01/2024 |
Project Phase
Planning and Project Approval
Last Updated
04/14/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Giffels-Webster Engineers
Construction Contractor
TBD