Englewood East Amenity Replacement
Last Updated: 05/07/2026 Category: Parks And Recreation Current Phase: Construction
Replacement and improvement of playground equipment and shade structure that was damaged during Hurricane Ian along with the installation of an additional pavilion and drinking fountain for community use.
Last Updated: 05/07/2026 Category: Parks And Recreation Current Phase: Construction
Creation of a master plan through the park design process and phase 1 development.Last Updated: 05/07/2026 Current Phase: Design Development
Replacement of boardwalk at Oyster Creek Environmental Park.Riverside Boat Ramp Replacement
Last Updated: 05/07/2026 Category: Parks And Recreation Current Phase: Construction
As part of the CMP, Community Services is conducting structural assessments on all piers, boardwalks, seawalls and boat ramps; through this assessment process it was bought to CS attention that Riverside Boat Ramp provides immediate safety concerns. During the site analysis the engineer determined the ramp could not be repaired in place; this project will be to design a replacement ramp that alleviates the safety issues.
South County Regional Park Playground Replacement
Last Updated: 05/07/2026 Category: Parks And Recreation Current Phase: Design Development
Replacement of the existing playground equipment that has reached it's of life cycle. This will include the 5-12 and 2-5 ages play structures. The existing shade canopies will remain and be incorporated into the new equipment layout. Final design's from 3 vendors will be shared with the community so they can vote on the most liked concept. The design with the most votes is what will be installed.Burnt Store Water Reclamation Facility Expansion
Last Updated: 05/01/2026 Category: Utilities Current Phase: Design Development
This expansion project will increase wastewater treatment capacity for the Burnt Store service area.
Disaster Recovery Site - Tom Adams Bridge Emergency Repair - Hurricane Milton
Last Updated: 05/01/2026 Category: Disaster Recovery Site
The Tom Adams Bridge sustained damage from Hurricane Milton, necessitating emergency repairs.
Sheriff Administration and Hardened 911 Facility
Completed Category: Sales Tax Funded Category: County Facilities
Design and construction of a new 62,000-square-foot Law Enforcement Administrative Headquarters for the Charlotte County Sheriff’s Office. This modern facility will be located on County-owned land adjacent to the existing District 3 Headquarters and the Impound, Evidence, and Forensics Facility, bringing multiple law enforcement services together into one coordinated campus.
The new headquarters will replace the current leased building, which was originally repaired after Hurricane Charley and remains vulnerable to severe weather. The upgraded facility will meet the needs of a modern, growing law enforcement agency by providing safer, more efficient, and more resilient space for deputies and staff to serve the community. It will also include a new Emergency 911 Communications Center, ensuring reliable emergency response during critical events.
Last Updated: 04/30/2026 Category: County Facilities Category: Sales Tax Funded Current Phase: Construction
Construction of a new 4 stall apparatus bay Fire Station on the NW corner of Tamiami Trail & Green Gulf Blvd at the Tuckers Grade intersection in Punta Gorda.