Learn about the ongoing repairs county departments are making to county roads, rights of ways, facilities, beaches, parks and libraries from damage caused by storms, including hurricanes Ian, Helene and Milton.
Disaster Recovery Projects DashboardEnglewood Beach Port Charlotte Beach Park Bayshore Live Oak Park
Weir Inspection and Repair Design
Last Updated: 08/22/2025 Category: Drainage Current Phase: Planning and Project Approval
The ELK 3.45, FOR 5.11 and a weir on the Pellam Waterway were found to be damaged. The cause of the damage is not known. An engineering firm has been retained to assess these three water control stuctures to determine the extent of the deficincies and then to prepare a cost effective plan that will successfully restore the structures so that they operate as designed.Lakeview/Midway Wastewater Expansion
Last Updated: 08/21/2025 Category: Utilities Current Phase: Design Development
This project proposes construction of a wastewater collection system to service approximately 1,500 properties with sewer service, new water service lines and a vacuum station that will provide sewer collection for the wastewater system.Last Updated: 08/20/2025 Category: Roadway Current Phase: Design Development
Flamingo/Edgewater Widening
Gasparilla Road Intersections Signalization
Last Updated: 08/20/2025 Category: Roadway Current Phase: Design Development
Signalization project for the intersection of Gasparilla Road and Rotonda East Boulevard and the intersection of Gasparilla Road and Ingram/Ingraham BoulevardsKings Hwy Harborview Rd Intersection Improvements
Last Updated: 08/20/2025 Category: Roadway Current Phase: Construction
Kings Hwy Harborview Rd Intersection Improvements. Traffic signal hardening.Mid-County Mini Transfer & Recycling Facility Roadway Reconfiguration and Truck Entrance
Last Updated: 08/20/2025 Category: Roadway Current Phase: Design Development
The design, permitting, and construction of a new gated access trucking road into the mini-transfer station.Riverside Boat Ramp Replacement
Last Updated: 08/20/2025 Category: Parks And Recreation Current Phase: Design Development
As part of the CMP, Community Services is conducting structural assessments on all piers, boardwalks, seawalls and boat ramps; through this assessment process it was bought to CS attention that Riverside Boat Ramp provides immediate safety concerns. During the site analysis the engineer determined the ramp could not be repaired in place; this project will be to design a replacement ramp that alleviates the safety issues.
Sheriff District 4 HQ, Training Facility and K9 Unit
Last Updated: 08/20/2025 Category: County Facilities Category: Sales Tax Funded Current Phase: Turnover and Closeout
Construction of a replacement District 4 Headquarters Facility with a training component and K9 kennel/training area replacing existing facilites. The district office will utilize the prototype layout from District 1. The training building area will be incorporated into a single facility. The facility will be constructed at the Airport Road Annex site, replacing the existing Sheriff's Training, Supervisor of Election and old Transit Facility .Harold Avenue Generator Mitigation Grant
Last Updated: 08/18/2025 Current Phase: Turnover and Closeout
This Mitigation Grant funded project will provide a permanent backup generator and enclosure for the Harold Avenue Recreation Center.