Project Status Updates

Hillsborough Boulevard Water Main Project News Image

Hillsborough Boulevard Water Main Project

Last Updated: 04/16/2026 Category: Utilities Current Phase: Construction

This project will install an eight-inch water main along Hillsborough Boulevard from Yorkshire Street to U.S. 41. The water main will be installed parallel to the Peace River Manasota Water Authority’s 42-inch Phase 2B Pipeline.

Read More

South County Regional Park Improvements -Design

South County Regional Park Improvements -Design Sales Tax Project

Completed Category: Parks And Recreation

Read More

Ainger Creek Boat Ramp Replacement News Image

Ainger Creek Boat Ramp Replacement

Last Updated: 04/14/2026 Category: Parks And Recreation Current Phase: Design Development

This project will improve the overall experience for boaters and visitors by enhancing traffic flow, expanding parking efficiency, and adding new amenities. A pre-manufactured restroom facility will be installed to provide greater convenience for users, and the boat ramp will be relocated to help reduce loading and unloading wait times. Together, these improvements will create a safer, more accessible, and more enjoyable waterfront experience for the community.

Read More

Mid County Transfer Station Wall News Image

Mid County Transfer Station Wall

Last Updated: 03/31/2026 Category: County Facilities Current Phase: Design Development

Read More

Supervisor of Elections Warehouse News Image

Supervisor of Elections Warehouse Sales Tax Project

Completed Category: County Facilities Category: Sales Tax Funded

Provide new 20,000 sq ft +/- facility up to current code, meet needs of required climate controlledspace by the Supervisor of Elections. The facility shall include climate-controlled storage area for sensitive polling equipment and related supplies and support staff. Must be readily accessible and support staff needs for monitoring tabulation. Preferably house SOE administrative offices and serve public visitation in the same location. Includes 10,000 sq ft for emergency managemet and facilities. 

Read More

East Port Water Reclamation Facility Expansion News Image

East Port Water Reclamation Facility Expansion

Last Updated: 02/23/2026 Category: Utilities Current Phase: Construction

This project includes the expansion of the current water reclamation facility to treat six million gallons of wastewater per day to nine million gallons per day. The project also includes advanced wastewater treatment, which is a valuable addition to the treatment process to ensure treated water has as low concentrations of nutrients as possible.

Read More

Water Tower News Image

Water Tower

Last Updated: 02/05/2026 Category: Utilities Current Phase: Planning and Project Approval

The Utilities Department is building its first ever water tower.

Read More

Disaster Recovery Site - Burnt Store Water Treatment Plant News Image

Disaster Recovery Site - Burnt Store Water Treatment Plant Disaster Recovery Project Site

Last Updated: 01/12/2026 Category: Disaster Recovery Site Category: Utilities

Hurricane Ian damaged many mechanical components and fencing to the Burnt Store Water Treatment Plant.

Read More

Disaster Recovery Site - Gulf Cove Water Booster Station News Image

Disaster Recovery Site - Gulf Cove Water Booster Station Disaster Recovery Project Site

Last Updated: 01/12/2026 Category: Disaster Recovery Site Category: Utilities

Hurricane Milton damaged the building's roof.

Read More