Project Status Updates

Public Works Ian Projects

Hurricane Ian Projects

Learn about the ongoing Public Works and Facilities repair projects to county roads, right of ways and facilities from damage caused by Hurricane Ian.

Hillsborough Boulevard Water Main Project News Image

Hillsborough Boulevard Water Main Project

Last Updated: 03/24/2025 Current Phase: Construction

This project will install an 8-inch water main along Hillsborough Boulevard from Yorkshire St. to US 41. The water main will be installed parallel to the Peace River Manasota Water Authority’s 42-inch Phase 2B Pipeline.

Read More

Dorchester Street Sidewalk

Dorchester Street Sidewalk

Last Updated: 03/13/2025 Category: Sidewalks Current Phase: Construction

 Dorchester Street Sidewalk

Read More

Harold Avenue Generator Mitigation Grant

Harold Avenue Generator Mitigation Grant

Last Updated: 01/31/2025 Current Phase: Turnover and Closeout

This Mitigation Grant funded project will provide a permanent backup generator and enclosure for the Harold Avenue Recreation Center. 

Read More

Cultural Center Replacement News Image

Cultural Center Replacement

Last Updated: 01/29/2025 Category: County Facilities Current Phase: Planning and Project Approval

The Cultural Center Replacement project was approved to move forward with masterplanning and programming by the Board of County Commissioners on March 12th 2024 following a series of public input activities and final presentation. The board granted $750,000 to proceed with advertising for a consultant. Additionally the direction was given to move forward with demolition of the existing facility scheduled for FY26. The full design and permitting phase is scheduled for funding in FY27 with construction funding in FY28.

Read More

William R. Gaines Jr. Veterans Memorial Park

William R. Gaines Jr. Veterans Memorial Park Sales Tax Project

Last Updated: 01/03/2025 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Complete

Design and construction of upland and wetland trails throughout William R. Gaines Jr. Veterans Memorial park.

Read More

NWPC Interior Canal Maintenance Dredge News Image

NWPC Interior Canal Maintenance Dredge

Last Updated: 09/20/2024 Category: Coastal Current Phase: Turnover and Closeout

Northwest Port Charlotte waterway maintenance dredge design project. Design, plan, and permit a limited dredge project for the MSBU.

Read More

Cape Haze Wastewater Expansion

Cape Haze Wastewater Expansion

Last Updated: 09/10/2024 Category: Utilities Category: Utilities Current Phase: Complete

Read More

Test Project

Test Project Sales Tax Project

Last Updated: 07/01/2024 Current Phase: Complete

Test intro

Read More

Ainger Creek Boat Ramp Replacement News Image

Ainger Creek Boat Ramp Replacement

Last Updated: 05/03/2024 Category: Parks And Recreation Current Phase: Design Development

This project consists of evaluating the site to improve traffic flow and to maximize parking, determining the best location for possible construction of a permanent restroom facility, and evaluating the current ramp to minimize buffering time for loading and unloading vessels.

Read More