Washington Loop over Prairie Creek Bridge Replacement
Last Updated: 07/13/2026 Current Phase: Design Development
Washington Loop Road Bridge over Prairie Creek - Bridge ReplacementWaterway Hurricane Debris Removal-Grant Funded
Last Updated: 07/13/2026 Category: Drainage Current Phase: Turnover and Closeout
Remove hurricane debris from approximately 37 miles of navigable waterways throughout the county.Weir Inspection and Repair Design
Last Updated: 07/13/2026 Category: Drainage Current Phase: Design Development
The ELK 3.45, FOR 5.11 and a weir on the Pellam Waterway were found to be damaged. The cause of the damage is not known. An engineering firm has been retained to assess these three water control stuctures to determine the extent of the deficincies and then to prepare a cost effective plan that will successfully restore the structures so that they operate as designed.Ainger Creek Boat Ramp Replacement
Last Updated: 07/10/2026 Category: Parks And Recreation Current Phase: Design Development
This project will improve the overall experience for boaters and visitors by enhancing traffic flow, expanding parking efficiency, and adding new amenities. A pre-manufactured restroom facility will be installed to provide greater convenience for users, and the boat ramp will be relocated to help reduce loading and unloading wait times. Together, these improvements will create a safer, more accessible, and more enjoyable waterfront experience for the community.
Last Updated: 07/10/2026 Current Phase: Design Development
The continued growth of Charlotte County requires an enhanced disaster response through a whole community approach and collaborative problem solving to ensure timely protective actions, a more educated, informed and prepared population and resilient infrastructure.
Harbor Heights Tennis/Pickleball Court Renovation
Last Updated: 07/10/2026 Current Phase: Construction
Reconstruction of the existing tennis/pickleball courts at Harbor Heights Park.Last Updated: 07/10/2026 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Construction
The existing pool at Port Charlotte Beach Park will be replaced with a community pool suitable for lap swimming, aerobic exercise, therapy, and other special events.
Port Charlotte Beach Recreation Center
Last Updated: 07/10/2026 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Construction
The project replaces the existing facility that has reached its end of life and suffered significant Hurricane damages.
Allapatchee Shores Park - Stormwater and Parking Enhancements
Last Updated: 07/09/2026 Category: Parks And Recreation Current Phase: Construction
Allapatchee Shores Park - Stormwater and Parking Enhancements