Disaster Recovery Site - Tom Adams Bridge
Last Updated: 04/01/2026 Category: Disaster Recovery Site
Hurricane Ian caused extensive damage throughout the site, including damage to roof, exterior areas, electrical and mechanical issues, sidewalks and structure.Last Updated: 04/01/2026 Current Phase: Design Development
The continued growth of Charlotte County requires an enhanced disaster response through a whole community approach and collaborative problem solving to ensure timely protective actions, a more educated, informed and prepared population and resilient infrastructure.
Last Updated: 04/01/2026 Category: Roadway Current Phase: Design Development
Flamingo/Edgewater Widening
Gasparilla Road Intersections Signalization
Last Updated: 04/01/2026 Category: Roadway Current Phase: Design Development
Signalization project for the intersection of Gasparilla Road and Rotonda East Boulevard and the intersection of Gasparilla Road and Ingram/Ingraham BoulevardsGasparilla Road/Pioneer Trail Sidewalk Extension
Last Updated: 04/01/2026 Current Phase: Planning and Project Approval
Last Updated: 04/01/2026 Category: Roadway Current Phase: Construction
Widen Kings Highway to a 4 lane divided roadwayKings Hwy Harborview Rd Intersection Improvements
Last Updated: 04/01/2026 Category: Roadway Current Phase: Construction
Kings Hwy Harborview Rd Intersection Improvements. Traffic signal hardening.Mid-County Library Hurricane Repairs
Last Updated: 04/01/2026 Category: County Facilities Current Phase: Turnover and Closeout
Utilizing the Hurricane repair consultant contract as well as the construction manager at risk for Mid-County repairs contract, design and restore the Mid-County Library to its condition prior to the event. Utilize the opportunity to make improvements to the facility where applicable following the guidelines of the County's insurance policy.Mid-County Mini Transfer & Recycling Facility Roadway Reconfiguration and Truck Entrance
Last Updated: 04/01/2026 Category: Roadway Current Phase: Design Development
The design, permitting, and construction of a new gated access trucking road into the mini-transfer station.